A January delivery of green coffee is rarely ordered in January, so it pays to count backwards from the day the bags must reach you.

If you want Indonesian green coffee in your warehouse in January, the order usually goes in well before the year ends. Nobody is being slow about it. A shipment has several stages that cannot be squeezed together, and each one carries some slack. Here is the sequence, worked backwards from the day the bags need to be at your door.

Start From the Arrival Date

Pick the date you actually need the coffee on your roasting floor, then subtract the last stretch first: customs clearance and trucking from the port, which can take a few days to a week or more depending on the country and whether an inspection is called. Before that comes the ocean leg. As a rough guide, allow four to seven weeks to Europe or the US and about two weeks to Japan. Ask your forwarder for a current estimate, because routing, transshipment and season all move it.

Before the Container Sails

Booking space with the shipping line, packing and loading the container, and preparing the shipping documents usually takes a week or two, longer in a busy season. A pre-shipment sample, drawn from the lot being packed, goes to you for approval before the coffee is loaded. Courier time for that sample can be a week by itself, and if you reject it the clock starts again.

The Front End: Samples and Contract

This is where most of the slack hides, because it depends on the buyer. An offer sample that arrives and sits uncupped for two weeks costs the same as a two-week shipping delay. Agree early on who approves the sample, how fast you will answer, and what happens if it is not right. Payment terms, such as a letter of credit or payment in advance, add days of their own, so ask about them at the start.

Leave a Buffer

Lunar New Year, Eid and the year-end holidays slow down ports, factories and offices at origin and destination, and the dates shift every year. Check the holiday calendars at both ends when you set your dates, and add a few weeks of buffer for any coffee you cannot run out of.